TITLE: |
||
|
|
|||
|
DOCUMENT ID: |
6110
Appendix T2 Special
Lock and Tag Removal Procedure |
||
|
|
|||
In accordance with Jefferson Lab procedures (ES&H Manual Chapter
6110 Appendix T1 Lock, Tag, Try (LTT) Procedure and ES&H Manual Chapter 6111
Administrative Control Using Locks and Tags) a lock
and/or tag is removed only by the Qualified Tagger who placed it on the equipment, or an authorized person in the administrative
control scenario.
Only when the Qualified Tagger is not physically on-site, or the
information is missing or illegible, is this special removal procedure to be
utilized.
|
NOTE: This procedure is to be used for removing a lock (maintenance or administrative) and/or a tag (maintenance or administrative) to which you are not the owner, nor listed as authorized to remove. |
This procedure is used for removing a lock (maintenance or administrative) and/or a tag (maintenance or administrative) when the owner(s) is not physically on-site, or the information is missing or illegible.
NOTE: Management authority may be delegated at the discretion of the responsible manager.
·
Recognize and respect LTT measures.
· Do not remove any lock or tag except those meeting the exceptions outlined within this appendix.
Unless otherwise stated anyone at Jefferson Lab may perform the process steps listed below.
Step 1: Attempt to Locate the Qualified Tagger
·
Verify that the Qualified
Tagger, if known, is physically not on-site.
Make a determined effort to locate the individual by email, telephone,
and pager.
|
NOTE: In no case is an email, telephone, or page to be considered as authorization for removal of a lock and/or tag. The “Special Lock and Tag Removal Form” below must be completed. |
·
Conduct a walk-through
inspection of the system and surrounding area to ensure no one is at risk from
restoration of energy.
·
Inform all affected
individuals of the pending lock/tag removal.
Step 3: Affirm Management Agreement
·
Complete the ES&H
Manual Chapter 6110 Appendix T2 Special Lock and Tag Removal Form.
·
Obtain approval
signature from:
o
One of the following:
§
Your work group
supervisor,
OR
§
Your department
manager.
AND
o
One of the following
(see NOTE below):
§
The original Qualified
Tagger’s supervisor,
OR
§
The original Qualified
Tagger’s department manager,
OR
§
The owner or primary
manager of the affected equipment.
|
NOTE: A verbal signature (i.e. an email or telephone conversation) is acceptable in critical situations when the approval signature person is away from the laboratory. The conversation must be documented in the corresponding approval signature block, stating when and with whom this conversation took place, or by attachment of a copy of the e-mail. |
·
Display a copy of the
completed form on, or closely adjacent to, the equipment,
AND
·
Display a copy of the
completed form on, or closely adjacent to, the area where the lock/tag was
removed (if different than above).
|
NOTE: The form(s) must remain in-place until the original Qualified Tagger removes it, or all reasonable efforts to identify and/or locate the lock/tag owner have been exhausted; then the equipment owner, with concurrence from the Qualified Tagger’s supervisor (if known), may remove it. |
Step 5: Remove the Lock and Tag
·
Remove the
device(s). Exercise caution so as not to
damage the components they are attached to.
Do not use any tool besides appropriately sized bolt cutters to cut a
lock.
·
Immediately –
Ensure the Qualified Tagger’s supervisor is notified and given a copy of the
removal form.
·
Before work is
resumed on the equipment – The Qualified Tagger’s supervisor notifies the
Qualified Tagger of the change in status.
5.0
Revision Summary
Revision 1.3 – 02/15/13 - Clarified verbiage. No substantive changes.
Revision 1.2 – 05/10/12 - Clarified verbiage. No substantive changes.
Revision 1.1 – 12/01/11 - Clarification of process steps and updates made to format. Qualifying periodic review, no substantive changes required.
Revision 1 – 04/04/09 – Update to reflect current laboratory operations.
|
ISSUING
AUTHORITY |
TECHNICAL
POINT-OF-CONTACT |
APPROVAL
DATE |
REVIEW
REQUIRED DATE |
REV. |
Page 1 of 4 |
|
ESH&Q Division |
04/04/09 |
04/04/14 |
1.3 |