Hall D collaborators,
We need to writeup a status/progress report on our Hall D effort to be
posted along with other institutional responses. Alex has recently sent
pointers to other reports, so you can see the level of detail which is
necessary.
Jlab - Institutional Status/Progress Report
-------------------------------------------
Projects:
1. Solenoidal Magnet
- Paul
2. Civil Construction
- Roger
3. Pipeline TDC development (F1)
- Chris, could you summarize the work so far with help from Fernando
and Ed?
4. Other, Interface with Jlab
- shepherding MOUs through procurement
Elliott could you put down a paragraph here?
Please send me a summary of each of these projects, so I can put it all
together.