[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Update 2 (fwd)
---------- Forwarded message ----------
Date: Tue, 05 Feb 2002 18:42:04 -0500
From: Eric Scott <ebscott@indiana.edu>
To: Task-d <task-d@dustbunny.physics.indiana.edu>,
Paul Brindza <brindza@jlab.org>, Elton Smith <elton@jlab.org>
Subject: Update 2
Hi all
Well another extraction day has finished:
A) We managed to get the LN2 Dewar down in one piece.
B) One of the LN2 vent lines has also been removed.
C) The dummy port on Puffing Billy was opened and the wads of super
insulation that had been stuffed inside were removed.
D) All racks were striped clean.
E) The top of Puffing Billy was stripped down, documented and the
wires secured, ports sealed.
Cheers,
Eric & Company