Hi all

    Well another extraction day has finished:

    A)  We managed to get the LN2 Dewar down in one piece.  
    B)  One of the LN2 vent lines has also been removed.  
    C)  The dummy port on Puffing Billy was opened and the wads of super 
insulation that had been stuffed inside were removed.
    D)  All racks were striped clean.
    E)  The top of Puffing Billy was stripped down, documented and the 
wires secured, ports sealed.
  