Meeting Wed Aug 23 8:45 F325




Dear collaborators,

We will have a brief meeting tomorrow morning at 8:45 in CC F325. Provided
it does not interfere with activities in the hall, we can review various
aspects of the beam test. Clearly installation activities should take
precedence.

o Announcements (all)
- comments on PAC

o Beam test
- TSOP (Eric)
- ESAD (Elliott)
- installation activities (all)
- run plan (Zisis, discussion)
- trigger setup (?)

o August deliverables
- FADC (Chris, Elton)
- auxiliary electronics (Elton)

....



Elton Smith