Re: helios Quads



Hello Elke,

Thanks a lot for your prompt reply and comments.
It would be great if Jim or you would be able to help
over. According to the P3E (and Eugene)  we would be
able to spend only about $10k before 2011 (not much at
all), if we decide to test (ship) it earlier.

Regarding the time scale, it depends on the BNL people
and Jim and your schedule/availability. If we can
test it at BNL we can ship it later. Alternatively, we can
ship it to the Jlab and test it here (which propably would be
more difficult); we need to find the storage here anyway.

Anyway, there is no rush at the moment.


Cheers,
        Sascha




On Fri, 29 May 2009, elke-caroline aschenauer wrote:

> On Thu, 28 May 2009, Alexander Somov wrote:
>
> Dear Sasha,
>
> let me make below some remarks.
> I'm sure Jim will make much more and much more substantial.
>
> cheers elke
>
>
>   Hi Jim,
>
>   I hope that your trip to the BNL went smoothly and you managed to recuperate
>   a bit from the moving disaster...
>
>   Before you start forgetting about the GlueX, let me ask
>   you a few quick questions.
>
>   We had a meeting with Ashot and Liping today; they consider
>   seriously joining the gluex collaboration and taking some responsibilities,
>   in particular, for the pair spectrometer.
>
>
>   A couple of questions arose regarding the pair spectrometer magnet:
>     - who should we contact with at BNL regarding a property
>     transfere (we will need to prepare corresponding documents)?
>
>     - it would probably make sense to test this magnet at BNL
>     (as you have pointed out) to be sure that it has
>      no 'serious' damages like coil shorts, water leak...
>      What do you think about this ?
>
> this is a difficult point. None of you is a user at BNL. Who do you have
> in mind doing this. If the BNL people should do it, JLab should be
> prepared to pay for it. If JLab people would do it they have to go through
> all the BNL training and we still need BNL manpower. I think somebody
> has to talk to Phil Pile to get a cost estimate for this and find out his
> team has time because there will be a big shutdown coming up for BNL and
> there is the construction of the NSLS-II going on.
> I'm sure Jim can do it, if he is to busy, I can do it, I'm in meetings
> with Phil at least twice a week.
>
>   Eugene mentioned that it would (probably) be possible to use some money,
>   allocated for the ps in 2011, earlier to check/ship the ps magnet to the
>   jlab. We also need to find a storage for the magnet at jlab.
>
> so what time scale are you talking about and how much money is there. I
> know I could look myself in P3e, but .......
>
>   I hope to see you soon during the tagger magnet review.
>
>   Cheers,
>          Sascha
>
>
>
>
>
> ( `,_' )+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=
>  )    `\                                                     -
> /    '. |                                                     +
> |       `,              Elke-Caroline Aschenauer               =
>  \,_  `-/                                                       -
>  ,&&&&&V         Brookhaven National Lab                         +
> ,&&&&&&&&:       Physics Dept.,            8 Shore Road           =
> ,&&&&&&&&&&;      Bldg. 510D / 2-195        East Patchogue, NY,     -
> |  |&&&&&&&;\     20 Pennsylvania Avenue                 11772-5963  +
> |  |       :_) _  Upton, NY 11973                                     =
> |  |       ;--' | Tel.:  001-631-344-4769   Tel.:  001-631-569-4290    -
> '--'   `-.--.   | Fax.:  001-631-344-1334   Cell:  001-757-256-5224     +
>   \_    |  |---'                                                        =
>     `-._\__/     Mail: elke@jlab.org                                     -
>            =-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=
>
>