FDC Weekly Meeting Agenda
May 22, 2008
-----------------------------
1. Full-scale prototype update.
- procurement update (outstanding items: HV capacitors,
rail assemblies, 2-mm Rohacell)
- update on progress in preparing the cathode board PR
- Update on review of design (Fernando/Roger)
- modification for reflections in model
- adding holes for gas/frame modifications
- Draft of PR
- Planning for 5 micron boards
- When will it be on Elke's desk?
- clean room update
- plans for occupying space
- status of procurement for granite tables
- status of procurement for second construction station
- short terms plans for wire frame construction
- modifications to construction jig for component clearance
- start of wire frame construction
- long term cathode board storage
- second Lucite box
- transport/storage box
2. Wire winding planning.
- progress update from IUCF
- next steps and planning for Phase 2 winding
3. Composite cathode prototype construction update.
- tensioned cathode construction progress
- flatness measurement update and plans
- upgrading to a 2-D automated scanning system.
- issues with single ground connection
4. Design modification: clearance for rigid flex assemblies.
5. Gas volume definition.
- impedance/flow calculation result updates
- definitions of holes in cathodes
- inclusion of gas windows in CAD model (Chuck)
6. Cathode board discussion. (Roger)
- soldering tests
- document for QA/stuffing/cleaning cathodes (Roger)
- document for QA/stuffing/cleaning cathode daughter boards (Roger)
7. STB/HVTB update. (Kim)
- document/instruction for board stuffing
8. Small-scale prototype test update.
- progress on defining specs for ASICs
- plans/timeline for preparing ASIC test writeup
- optical measurement of 2 micron cathode edge
9. Wire quality document.
10. Frame construction procedure document review.
11. Design of gas handling system.
**********************************************************************
**********************************************************************
* *