[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Next FDC Group Meeting





Folks,

The next FDC group meeting is scheduled for tomorrow afternoon in
F326 at 1:30 p.m.. The agenda is given below.


 				  Regards,

 					Daniel

**********************************************************************
FDC Weekly Meeting Agenda
July 16, 2009
-----------------------------
1. Full-scale prototype preparations
     - status of ground cables
     - update on gas window construction
     - stack construction
        - status of assembly jig
        - assembly document status
        - status of parts 'n pieces
        - work in clean room
2. Wire frame update
     - soldering repairs on wire frames
        - schedule
     - wire frame cleaning update
     - Phase 3 planning
        - dealing with flatness issues
        - design of combs
        - new strongback design
        - other facility modifications
        - final circuit board design
        - time table for construction
     - update of construction document
        - wire electroplating procedures
3. Cathode frame update
     - cathode frame gas sealing
     - cathode flatness measurement status
        - granite table baseline
     - cathode construction updates
        - construction of cathode boards
        - construction of sandwiches
        - layout of boards in prototype
     - short term storage plans (inert environment)
     - rigid-flex assembly component soldering update
     - rigid-flex assembly attachment
        - test soldering
        - schedule for completing work
     - PR for 2-um board material for production
     - cathode construction document status
     - document for QA/soldering/cleaning cathodes
     - document for QA/stuffing/cleaning cathode daughter boards
4. Miscellaneous
     - LV, HV, signal cable update
         - shield/braid questions
     - cooling system test report
     - HV connections to packages
     - sense and field wire test document
        - testing of production wire order
     - remaining FDC system design work
     - FDC construction clean room location update
5. Prototype tests
     - update on cosmic ray stand
     - small-scale prototype resolution study update
     - test plan for full-scale prototype
     - fixture for support/rotation of full-scale prototype
**********************************************************************
**********************************************************************
*                                                                    *
* Dr. Daniel S. Carman                   e-mail : carman@jlab.org    *
* Staff Scientist                        office : (757)-269-5586     *
* Jefferson Laboratory                   web: www.jlab.org/~carman   *
*                                                                    *
**********************************************************************