Hall D Updated Concept Submittal - Review Comments Requested (fwd)




Hi Eric, collaborators,

The A&E firm has provided their concept submital. We need to give feedback
by Monday. The files are available at

http://www.jlab.org/Hall-D/civil/drawings/design35/

I think we will need a phone conference at least between Eric and JLab
folks to review and consolodate any comments to pass on to Civil. Due to
the short time frame, I suggest we collect comments over the weekend and
review them on 1:30 on Monday afternoon. If there are any others that
should take a look at the drawigs, pass them on and have them send
comments to me.

Cheers, Elton.

Elton Smith
Jefferson Lab
elton@jlab.org
(757) 269-7625

---------- Forwarded message ----------
Date: Wed, 1 Mar 2006 13:35:09 -0500 (EST)
From: Elton Smith <elton@jlab.org>
To: Eric Scott <ebscott@indiana.edu>
Cc: Elton Smith <elton@jlab.org>, Elliott Wolin <wolin@jlab.org>
Subject: Hall D Updated Concept Submittal - Review Comments Requested (fwd)


Hi Eric,

We probably need to have a phone conference to go over any comments on
this submittal and make sure that all our concerns are covered. I have
place the files indicated below at the following location for ease of
access:

http://www.jlab.org/Hall-D/civil/drawings/design35/

Let me know if there is any problem viewing them.

Cheers, Elton.


Elton Smith
Jefferson Lab
elton@jlab.org
(757) 269-7625

---------- Forwarded message ----------
Date: Wed, 01 Mar 2006 13:14:14 -0500
From: Rebecca Yasky <ryasky@jlab.org>
To: Elton Smith <elton@jlab.org>, Elliott Wolin <wolin@jlab.org>
Cc: Suresh Chandra <chandra@jlab.org>, Celia Whitlatch <whitlatc@jlab.org>,
     pavel@jlab.org, abkemeier <abkemeie@jlab.org>,
     Will Brooks <brooksw@jlab.org>
Subject: Hall D Updated Concept Submittal - Review Comments Requested

Elton, Elliott, & Erik,
We have received the Updated Concept Submittal (Updated Concept Dwgs and
Design Analysis) from the A-E..  Comments are due to me on March 6,
2006.  Here are links to the Drawings file:///M:/planteng/12
GeV/Design/Hall_D_Design/Concept_Update/Concept_Submittal/Drawings/HALL-D_Concept_Dwg_Feb06.pdf
<imap://ryasky@mail.jlab.org:993/fetch%3EUID%3E/Drafts%3E215?part=1.1.1.2&filename=HALL-D_Concept_Dwg_Feb06.pdf>
and the Design Analysis   file:///M:/planteng/12
GeV/Design/Hall_D_Design/Concept_Update/Concept_Submittal/Design_Analysis/Design
Analysis 2-28-06.pdf
<imap://ryasky@mail.jlab.org:993/fetch%3EUID%3E/Drafts%3E215?part=1.1.1.3&filename=Design%20Analysis%202-28-06.pdf>.
Also, attached is a review comment form that you have the option to
use.  To optimize your review effort, Facilities Management will review
the Design Analysis and I will send a separate email (tomorrow)
indicating the section(s) we want you to specifically review for
concurrence and/or comments.

I will be providing hard copies of half-size drawings to:

    * Elton Smith
    * Erik Abkemeier.

Some of your previous comments have not been incorporated due to my
delay getting the info to the A-E.  Please see my responses to your
earlier comments in blue below.  You do not need to repeat these comments.

If you have any questions, please feel free to call me.
Rebecca

Concept_Update_Review_Cmts.doc