[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Re: Status update



Fernando,

Digital board prototype - printed boards received, parts on order, 
quotes from vendors to populate 3 boards received, one chosen, 
anticipated delivery date Dec. 31, 2008.  Debugging begins 1/2009.

Analog board design - schematics and layout complete, one prototype 
wired on bench and tested, design changes resulting from tests underway 
to improve response time, estimated time for order of 3 prototype 
printed boards 1/2009, estimated time for receipt of one populated board 
from vendor 5/2009.

Richard Jones


Fernando J. Barbosa wrote:
> Hi Richard,
>
> I am updating my schedules and I would like to get a brief status 
> update on the Digital and Analog boards for the Tagger.
>
> Thanks,
> Fernando