Hi Richard,
Thanks for the update. I will update my schedules accordingly.
Regards,
Fernnado
Richard Jones wrote:
> Fernando,
>
> Digital board prototype - printed boards received, parts on order,
> quotes from vendors to populate 3 boards received, one chosen,
> anticipated delivery date Dec. 31, 2008. Debugging begins 1/2009.
>
> Analog board design - schematics and layout complete, one prototype
> wired on bench and tested, design changes resulting from tests
> underway to improve response time, estimated time for order of 3
> prototype printed boards 1/2009, estimated time for receipt of one
> populated board from vendor 5/2009.
>
> Richard Jones
>
>
> Fernando J. Barbosa wrote:
>> Hi Richard,
>>
>> I am updating my schedules and I would like to get a brief status
>> update on the Digital and Analog boards for the Tagger.
>>
>> Thanks,
>> Fernando
>