GAS-1 ASIC submission and collaboration meeting



Hi Mitch,
  I'd just like to try and clarify a few things since there is a MOSIS 
submission date of April 9 and a GlueX collaboration meeting of March 28-31 
happening close together.
  You mentioned before that everything has to be ready two weeks before the 
submission deadline which brings it back to March 26 which is before the 
collaboration meeting. Is it possible to provide some information on the 
design to the collaboration before that so that interested people can 
review/comment/approve before it's too late? The results of this would give 
us more definite information to go into the collaboration meeting with.
  A few other questions:
1. If the design is submitted April 9 do you know how long the production 
cycle will be?
2. Design improvements for the next version.
  a.) Selectable Gain of five (needed for positive cathode signals mostly). 
How long would it take to design and could it start before the GAS-1 has 
been tested? Estimated cost?
  b.) Selectable Discriminator. How long would it take to design and could 
it start before the GAS-1 is tested? Estimated cost? We're not sure whether 
we need a one-shot or time-over-threshold type output. We might know that 
after the collaboration meeting.
  c.) Would you expect to work on both of the above for the next version of 
the ASIC and if not which one would you prefer to do first? I expect that 
the collaboration will have an opinion about which item has the most 
priority.

Thanks, John