[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Next FDC Group meeting





Folks,

The next FDC group meeting is scheduled tomorrow at 1:30 p.m. in
F326.  The agenda is given below.  Also if you cannot attend the
meeting and are actively working on an FDC-related project, please
let me know and give me an update on the status of your work.


 				Regards,

 					Daniel

********************************************************************
FDC Weekly Meeting Agenda
December 4, 2008
-----------------------------
1. Full-scale prototype update.
     - procurements:
        - status of rigid-flex assembly PR
          - design review
        - status of Rohacell order
        - status of G10 order
        - update on FDC prototype spreadsheet
     - sense and field wire testing
        - QA test (mechanical, SEM) status
        - communication problem with procurement
2. Wire frame update.
     - wire frame construction:
        - PCB ring lamination
        - construction procedure document updates
        - specification/tolerance document
        - other wire frame related work
     - document/instruction for board stuffing + cleaning
3. Cathode construction update.
     - cathode R&D schedule update
     - cathode R&D work
        - construction procedure document/outline
        - in situ tension measurements
        - update on glue strip design
        - new prototype cathode
           - test results
     - flatness measurement system:
        - alignment issue update
        - measurement update
        - transfer of knowledge
        - documentation
     - update on cutting cathode edges
        - PR status
        - test plans
     - ground connections to cathode
     - ground plane attachment status
     - document for QA/stuffing/cleaning cathodes
     - document for QA/stuffing/cleaning cathode daughter boards
4. Miscellaneous
     - spacer frame update
        - epoxy tests
        - one vs. two o-rings
     - cooling system test report
     - HV connections to packages
5. Small-scale prototype test update.
     - ASIC updates
     - resolution study update
     - relocation of test stand
     - reorganization of 126
**********************************************************************
**********************************************************************
*                                                                    *
* Dr. Daniel S. Carman                   e-mail : carman@jlab.org    *
* Staff Scientist                        office : (757)-269-5586     *
* Jefferson Laboratory                   web: www.jlab.org/~carman   *
*                                                                    *
**********************************************************************