[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Next FDC Group meeting





Folks,

Welcome back to the happiest place on earth!  Our next FDC group meeting
will take place tomorrow at 1:30 p.m. in F326.  The agenda is given below.

REMINDER: please send updates on the cathode R&D schedule progress to
Chuck Hutton before the day is over (Brian, Mark, Bill, Dave, Eugene)
so that he can update the schedule by the time of the meeting. Talk to
me or Chuck if you have any questions on this.


 				Regards,

 					Daniel

**********************************************************************
FDC Weekly Meeting Agenda
January 8, 2009
-----------------------------
1. Full-scale prototype update.
     - procurements:
        - status of rigid-flex assembly PR
     - sense and field wire testing
        - QA test document
2. Wire frame update.
     - wire frame construction:
        - construction procedure document updates
        - update on wire frame construction
        - time line for IUCF frames
     - document/instruction for board stuffing + cleaning
3. Cathode construction update.
     - update on cathode construction document work
     - cathode R&D schedule update
     - cathode edge cutter
        - assembly of parts n' pieces
        - test plans and measurements
        - timeline for cutting first 5 micron boards
     - cathode R&D work
        - plans for construction of full cathode sandwich prototype
        - ground plane attachment and connections
        - ground connections to cathode
        - machining of pockets and placement of rigid-flex assemblies
            - possible design changes
     - update on cathode handling plans/tests
     - update on stretching of 2-micron board
     - flatness measurement system:
        - measurement update
        - transfer of knowledge
        - documentation
     - timeline for 5 micron prototype
     - document for QA/soldering/cleaning cathodes
     - document for QA/stuffing/cleaning cathode daughter boards
4. Miscellaneous
     - spacer frame update
        - R&D work
     - cooling system test report
     - HV connections to packages
5. Small-scale prototype test update.
     - resolution study update
     - update on reorganization of EEL 126
     - update on cosmic ray stand movement
**********************************************************************
**********************************************************************
*                                                                    *
* Dr. Daniel S. Carman                   e-mail : carman@jlab.org    *
* Staff Scientist                        office : (757)-269-5586     *
* Jefferson Laboratory                   web: www.jlab.org/~carman   *
*                                                                    *
**********************************************************************