I have a suggestion for the agenda list because several of the modules
listed do not exist.  I propose three sections outlined below and
hopefully we can consolidate these topics to reflect what will be
presented at the review.

Trigger and Data Acquisition Systems
Level 1 (Creates the experiment trigger)
     FADC250
     (Crate) Energy Sum
     SubSystem Processor
     Global Trigger Processor
     Fiber Optic Distribution(Energy Sum)

  Trigger/Clock/Synchronization Distribution
     Trigger Supervisor
     Clock/Trigger Fanout
     Fiber Optic Distribution(Clock/Trigger/Sync)

  Data Acquition
     Data rates
     Event Building
     Network layout (Includes ROCs, Slow Control, and TermServers)

The specifications and details of circuit board schematics, circuit board
layouts, parts lists/costs  etc can be included for each section listed
above.

The present activities are focussed on designing the modules for the
'test_stand'.  We have the two 20 slot VXS crates, and will produce at
least four more FADC-250 modules so that we can test a variety of
configurations with the new CODA libraries.  The prototype Trigger
Interface module will be used to provide test capabilities for the
proposed fiber optic distribution of the clock and trigger signals for the
two crate test stand.

Thanks,
Chris
~~~~~~~~~~~~~~~





On Wed, 5 Mar 2008, Fernando J. Barbosa wrote:

> Hello everyone,
>
> We will have our next meeting towards the upcoming Hall D system review
> in May next week This meeting takes place during the regular Hall D
> On-line meeting slot (F326/327 @ 2:00 p.m.). You may also recall that
> there is a requirement for 80% design completion for the CD-3 review
> this Summer.
>
> The goals of these meetings are to review the status, schedules and
> costs with the emphasis on, but not limited to, the technical aspects,
> requirements and specifications of the trigger system and signal
> distribution. These are the areas that require the most input at this
> time. We also need to consider supporting infrastructure with regards to
> testing of the various modules by the end-users.
>
> The following is the agenda for this portion of the meeting (other
> On-line items will be discussed):
>
> 1. Trigger System Diagrams
> 2. Signal Distribution (Global, VXS, Clock, Trigger, etc.)
> 3. Signal Distribution (SD) Module
> 4. Trigger Interface (TI) Module
> 5. Energy Sum (ES) Module
> 6. Energy Sum Processor (ESP)
> 7. SubSystem Processor (SSP)
> 8. Tagger Energy Processor (TEP)
> 9. Global Trigger Processor (GTP)
> 10. Track Subsystem Processor (TSP)
> 11. Global Trigger Crate
> 12. Software Support  & CODA
> 13. Test Strategies
>
> Suggested Documentation for the updates are as follows:
>
> 1. Description of the system or module - describes the operation and/or
> shows where it is applied
> 2. Specifications - should be comprehensive but emphasize the main tasks
> 3. Diagrams - system, block, wiring, etc.
> 4. Schematics
> 5. PCB
>
> I have created the appropriate directories in the M drive:
>
> 1. For most of this documentation, place your files in
> M:\halld\Electronics\Documents\TRIGGER or
> M:\halld\Electronics\Documents\SIGNAL_DISTRIBUTION (for clock, trigger,
> reset, distribution, etc. only).
>
> 2. For schematics and PCB CAD files, place your files in
> M:\halld\Electronics\PCBs\TRIGGER or M:\halld\Electronics\PCBs\SIGNAL
> _DISTRIBUTION.
>
> Regards,