JLab Hall D project staffing needs
JLab Hall D Project Staffing Needs
----------------------------------
E.Wolin
9-feb-2001
This note is an addendum to my previous note on JLab construction
staffing needs ("JLab Hall D Staffing Needs", 15-nov-00). Below I
estimate the number of project staff needed during construction and
installation of Hall D, excluding temps. In the previous note I
covered permanent staff.
I only cover mechanical, electrical, and electronics staff. I base my
estimates on Paul Brindza's original estimates.
TDY means "termpory duty", i.e. someone temporarily assigned to Hall D
from another department.
Below I assume the "fast track" scenario for Hall D construction
(slightly earlier completion than in my previous note). The
information below also appears in Elton's Hall D cost/manpower
spreadsheet. Note that under this scenario no project staff are
needed after FY06.
-----------
Spreadsheet
-----------
Funding Year | 01 | 02 | 03 | 04 | 05 | 06
Hall D Staff (TDY)
------------------------
Plant engineer | | 1 | 1 | 1 | |
------------------------------------------------
Subtotal | | 1 | 1 | 1 | |
Hall D Staff (Project)
------------------------
Mechanical designer | | 0.5 | 2 | 2 | 2 | 1
Mechanical technician | | | | | 1 | 1
Welder | | | | | 1 | 1
Electrical technician | | | | 1 | 3 | 2
------------------------------------------------
Subtotal | | 0.5 | 2 | 3 | 7 | 5
------------------------------------------------
Total | | 1.5 | 3 | 4 | 7 | 5
------------------------------------------------
begin:vcard
n:Wolin;Elliott
tel;fax:757-269-5800
tel;home:757-229-2724
tel;work:757-269-7365
x-mozilla-html:FALSE
org:Jefferson Lab;Physics Department
version:2.1
email;internet:wolin@jlab.org
title:Physicist
note:A218 CEBAF Center
adr;quoted-printable:;;12000 Jefferson Ave MS12H=0D=0A;Newport News;VA;23606;US
x-mozilla-cpt:;21408
fn:Elliott Wolin
end:vcard