[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Re: tof issues to add to tracker



Hall D PID Mail List:

On Fri, 28 Mar 2008, Elton Smith wrote:

Dear Elton,

thanks a lot for the summary.
I think the idea of the fine-mesh pmts is nice. Actually I personaaly
think we should buy one or two so we can do rate and gain tests. see the
signal shapes and all we need to know.

cheers elke



> Date: Fri, 28 Mar 2008 09:32:18 -0400 (EDT)
> From: Elton Smith <elton@jlab.org>
> To: beni zihlmann <bzihlman@indiana.edu>,
>      Matthew Shepherd <mashephe@indiana.edu>
> Cc: halld-pid@jlab.org
> Subject: tof issues to add to tracker
>
> Hall D PID Mail List:
>
>
> There have been several issues that came up in preparations for the review
> which we need to add to our action item tracker.
>
> * Updated magnetic fringe field in the vecinity of the scintillators.
> (George Biallas expects to have some results in the next month).
> * The design presented at the review included a soft iron shield 2.75 mm
> thick and a mu-metal 0.4 mm thick.
> - The total size of the pmt (5.35cm max)+ 2x0.275cm + 2x0.04cm = 5.98cm.
> - Nominal size of scintillator paddle is 6 cm, which implies this only fit
> if there are no gaps between pmt and shields.
> -> This is not a realistic design for the pmt housing, as the pmt (at HV)
> must be insulated from the housing (at ground). If we want to put the
> mu-metal shield at HV this is will require additional space.
>
> Options:
> 1. Elke has suggested that we might want to overlap the scintillators
> to avoid any inefficiencies and this would allow additional room
> for a realistic housing.
> 2. An alternative possibility would be to reconsider using fine-mesh pmts.
> This option would avoid the need for magnetic shielding and could fit into
> the current space. One would need to evaluate the cost trade-off between
> vacuum pmt + magnetic shielding compared to the single wire-mesh pmt. For
> this case, a realistic assessment of any inefficiencies due to tracks
> hitting between two scintillators would have to be made.
>
>
> Elton Smith
> Jefferson Lab MS 12H5
> 12000 Jefferson Ave
> Suite # 16
> Newport News, VA 23606
> elton@jlab.org
> (757) 269-7625
> (757) 269-6331 fax
>
>

 ( `,_' )+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=
  )    `\                                                  -
 /    '. |                                                  +
 |       `,              Elke-Caroline Aschenauer            =
  \,_  `-/                                                    -
  ,&&&&&V         Jefferson Lab                                +
 ,&&&&&&&&:       HALL-D 12C / F381       121-A Atlantic Avenue =
,&&&&&&&&&&;      Suite 8                 Hampton, VA 23664      -
|  |&&&&&&&;\     12000 Jefferson Ave                             +
|  |       :_) _  Newport News, VA 23606  Tel.:  001-757-224-1216  =
|  |       ;--' | Mail:  elke@jlab.org    Mobil: 001-757-256-5224   -
'--'   `-.--.   |                                                    +
   \_    |  |---' Tel.:  001-757-269-5352                             =
     `-._\__/     Fax.:  001-757-269-6331                              -
            +=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+