[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Next FDC group meeting





Folks,

Our next FDC group meeting is scheduled for tomorrow at 1:30 p.m.
in F326/327.  The agenda is given below.


				Regards,

					Daniel

**********************************************************************
FDC Weekly Meeting Agenda
July 31, 2008
-----------------------------

1. Full-scale prototype update.
    - Cathode boards:
      - electrical testing document (feedback)
      - plans for cutting cathode edges
    - JLab machine shop work submission
    - clean room update
       - status of procurement for granite table
       - occupancy of other group
    - wire frame construction
       - modifications to construction jig for component clearance
       - status of second construction station
       - plans for construction and time table for completion
       - A frame loan agreement
       - construction procedures document feedback
       - pockets for rigid flex assembly clearance
    - procurement updates
       - second Lucite box
    - R&D planning for cathodes
    - cooling system test report
    - radial size of spacer ring
2. Wire winding planning.
    - update from IUCF on Phase 1 winding
    - update on mask delivery
    - droop of wire frame
3. Composite cathode prototype construction update.
    - flatness measurement update
       - redesign of scanning system
       - plans for system procurements
    - ground connections to cathode
    - ground plane attachment status
    - construction procedure document
    - new tension measurements
    - technique to tension cathode to specific value
4. Cathode board discussion.
    - document for QA/stuffing/cleaning cathodes
    - document for QA/stuffing/cleaning cathode daughter boards
5. STB/HVTB update. (Kim)
    - document/instruction for board stuffing
6. Small-scale prototype test update.
    - progress on defining dynamic range for cathode/anode ASICs
    - ASIC studies writeup (Simon, Fernando)
    - update on x/y plots with 2 um cathodes and pulser calibrations.
7. Wire quality document.
8. Design of gas handling system.
**********************************************************************
**********************************************************************
*                                                                    *
* Dr. Daniel S. Carman                   e-mail : carman@jlab.org    *
* Staff Scientist                        office : (757)-269-5586     *
* Jefferson Laboratory                   web: www.jlab.org/~carman   *
*                                                                    *
**********************************************************************