[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Next FDC Group Meeting
Folks,
As announced last week, there will be no FDC Group meeting this week
due to the collaboration meeting that starts tomorrow. Our next
meeting will be on September 25. A quick update on progress:
1). Our first shipment of cathode boards from Allflex arrived. They
look very good. Electrical QA checkout has been completed on
all boards with no failures or problems.
2). The load test on our modified composite wire frame has been
completed with good results. We are working on some minor
modifications to the wire frame circuit boards that will be
completed this week. We will then begin wire frame construction.
3). We had a teleconference with IUCF yesterday and have agreed to
move to put the Phase 2 wire winding contract in place in the
next several weeks.
4). All parts for the cathode flatness measurement system are in house.
Final assembly will take place this week and measurements will
begin next week.
Regards,
Daniel
**********************************************************************
* *
* Dr. Daniel S. Carman e-mail : carman@jlab.org *
* Staff Scientist office : (757)-269-5586 *
* Jefferson Laboratory web: www.jlab.org/~carman *
* *
**********************************************************************